Our Work

Civil Site

Close
Civil Site

Mill Creek Site Improvements

Salem, Oregon

Site improvements for the mass earthwork phase of this development for a master planned 548 industrial site in Salem Oregon. 

Close Project
  • + 600,000 Cubic Yards of material to be relocated in just over 2 months
  • + Productivities for our fleet of earthmovers reached over 25,000 CY per day in peak conditions
  • + Kerr actively seeks projects where our vast resources of equipment can accelerate the completion of a project
Close
Close
Close Project
Civil Site

Colwood Site Improvements

Portland, Oregon

Kerr Contractors was the selected site work subcontractor for the early development for a new USPS Distribution Facility. 100,000 CY of earthmoving in wet weather conditions made economical with our in-house cement amending of the soils. Our Low Ground Pressure (LGP) Catepillar Challengers were able to efficiently relocate the onsite soils during weather not typical for earthmoving. The work included developing a large wetland mitigation of an existing golf course and associated public infrastructure improvements to facilitate the incoming project.

Close
Close
Civil Site

South Cooper Mountain High School

Beaverton, Oregon

Kerr Contractors was the selected site work contractor for the development of the new South Cooper High School in Beaverton Oregon for Hoffman Construction. The $185 Million Project is the largest school in the state of Oregon by capacity and building size. 500,000 CY of earth was moved including elements of hard rock excavation to grade the 47 acre site. The project included underground utilities like sanitary sewer, storm water and waterlines & connections. Public sanitary trunk lines and a 24” water transmission main allow for the ongoing development in the surrounding community. We developed an aggregate base for new streets and parking areas and also built 35,000 square feet of MSE retaining walls to maximize the playing surface for over 10 acres of artificial sports fields

Close Project
  • + 500,000 CY of earth was moved including elements of hard rock excavation to grade the 47 acre site
  • + Underground utilities including sanitary sewer, storm water and waterlines & connections
  • + Public sanitary trunk lines and a 24” water transmission main to allow for the ongoing development in the surrounding community
  • + Aggregate base for new streets and parking areas
  • + 35,000 square feet of MSE retaining walls to maximize the playing surface for over 10 acres of artificial sports fields
Close
Close
Close Project
Civil Site

Portland Airport Snow Removal

Portland, Oregon

Kerr Contractors has performed snow removal for the Port of Portland for over eight years including on-call services for snow removal at all aprons and service roads. Our crews work 12 hour shift, 24 hours a day, weekends, holidays and super bowls.

Close
The Kerr Way

Great results happen through teams.

We are passionate about what we do every day. Our five Core Values are the cornerstone which we refer to as “The Kerr Way”. These Core Values provide, without question, the standards by which we conduct ourselves.

link