Molalla TSC Hwy 213 Access Improvements
Tractor Supply needed to construct a road widening and left turn pocket on OR 213 to support their new location in Molalla. Work was coordinated with the Oregon Department of Transportation for road closures necessary to install an 8 FT x 10 FT box culvert, replacing an existing steel culvert. Other work creek and channel improvements, road widening, and added illumination. All work in Bear Creek was performed during the 60-day, in-water work window.
- Traffic control for Highway closures on OR 213 during construction
- Temporary signal
- 70 FT of 8 FT x 10 FT concrete box culvert
- Creek restoration, including fish rock and root wads
- 1,300 TONS aggregate base
- 970 TONS of HMAC
The Kerr Way
Kerr Contractors meets all challenges as a team. This includes specialists from within the organization and from trusted resources outside the company. Teams built from from the same values and corner stone produce high quality with speed.
Everything we do is based upon the simple idea that we do the right thing for our customer, no matter the cost. We do this for ourselves and everyone we work with on the team.
Kerr Contractors was founded on the belief that finding a better way is not just a matter of distinction, but of survival. The culture is built upon the passion of finding a better way to deliver everything we do.
Each action builds on the idea that you own it until you deliver it. The culture that permeates the company strives to hold everyone accountable and to set a high standard of conduct and accomplishment.
Your success is built upon enduring relationships with trusted construction specialists. These strong relationships deliver value to the customer and spawn future growth and opportunity.