Cornelius Pass Road Extension
Two sections of the Willamette Water Supply Program pipeline at Reed’s Crossing were installed in coordination with improvements being made to Cornelius Pass Road. A portion of the pipeline was placed under the Cornelius Pass/TV Highway intersection in coordination with the improvements being made to the Cornelius Pass/TV Highway Intersection project. Another portion of the pipeline was placed in the future Cornelius Pass Road extension, south of TV Highway. The pipeline consists of over 3,850 lineal feet of 48” welded steel pipe including valves, turn-outs and connections.
- Pipe was approximately 3,850 lineal feet of new 48″ welded steel
- Pipe is part of overall Willamette Water Supply Program new 30 miles of pipe from Wilsonville to Hillsboro
- Project was a coordinated effort between a private developer for the South Hillsboro Master Planned Community and the Willamette Water Supply Program
The Kerr Way
Kerr Contractors meets all challenges as a team. This includes specialists from within the organization and from trusted resources outside the company. Teams built from from the same values and corner stone produce high quality with speed.
Everything we do is based upon the simple idea that we do the right thing for our customer, no matter the cost. We do this for ourselves and everyone we work with on the team.
Kerr Contractors was founded on the belief that finding a better way is not just a matter of distinction, but of survival. The culture is built upon the passion of finding a better way to deliver everything we do.
Each action builds on the idea that you own it until you deliver it. The culture that permeates the company strives to hold everyone accountable and to set a high standard of conduct and accomplishment.
Your success is built upon enduring relationships with trusted construction specialists. These strong relationships deliver value to the customer and spawn future growth and opportunity.